Amit and Sunil together can complete a work in 9 days, Sunil and Dinesh together can complete the same work in 12 days, and Amit and Dinesh together can complete the same work in 18 days. In how many days will they complete the work if Amit, Sunil and Dinesh work together?
Pipes A, B and C can fill a tank in 15, 30 and 40 hours, respectively. Pipes A, B and C are opened at 6 a.m., 8 a.m. and 10 a.m., respectively, on the same day. When will the tank be full?
Two objects are moving on a circular path of length 160 km at a speed of 30 kmph and 50 kmph in the opposite direction. At how many point will both the objects meet on a circular path if they are continuously moving?
Two pipes can fill a tank in 10 and 14 minutes respectively. A third pipe can empty the tank at the rate of10 liters/minute. If all the pipes working together can fill the empty tank in 8 minutes, what is the capacity of the tank?