, Avg: 00:59 , 83%✓ SSC CHSL 202131)A completes 20% of a work in 5 days and B completes one-third of the work in 5 days. They began the work together but B leaves after 3 days. The total number of days needed for completion of the work is:
20
, Avg: 01:08 , 100%✓ SSC CHSL 202132)Varun and Gaurav can dig a pond in 10 days and 18 days, respectively. After finishing that work together, they receive an amount of Rs.7,280. What is the share of Gaurav in that amount?
Rs. 2,600
, Avg: 01:01 , 88%✓ SSC CHSL 202133)A and B can complete a piece of work in 27 days and 54 days, respectively. They completed the work in 9 days with the help of C. How many days will C take to complete eight-ninths of the work alone?
16
, Avg: 01:02 , 80%✓ SSC CHSL 202134)Anu can complete a piece of work in 22 days. Shama is 60% more efficient than Anu. How many days does Shama alone take to complete the same piece of work?
\(13\frac{3}{4}\)